Overview
Construct a bulk petrochemical storage facility with 28 pressurised storage tanks, pipeline integration to the nearby refinery, and full fire-suppression and spill-containment systems. The facility must meet DPR and international API standards.
Project Facts
- Location
- Effurun, Delta State
- Client
- Delta Petrochemicals Ltd
- Project Type
- Industrial
- Status
- Ongoing
- Duration
- 30 Months
- Completion Date
- Expected Q2 2025
- Services
- Design & Build · Pressure Vessel Installation · Pipeline Integration · Fire Suppression · Spill Containment
- Structural Engineer
- NOTGATE Industrial + German Partners
- Team Size
- 380 workers at peak
The Challenge
Petrochemical construction requires extreme precision in welding, pressure testing, and safety systems. The site is in the Niger Delta with challenging logistics and security considerations. 28 pressurised tanks, each holding 5,000 metric tonnes, required specialised foundation design and seismic bracing.
The Solution
NOTGATE partnered with a German tank manufacturer for the pressurised vessels and trained 60 local welders to ASME certification standards. A dedicated security perimeter with 24/7 monitoring was established before construction began. Foundation piles were driven to 35 metres to reach stable bedrock below the delta alluvium.
Project Gallery

Project Impact
Currently 65% complete with all 28 tank foundations finished and 18 tanks erected. The facility is on track for Q2 2025 commissioning and will become the largest private petrochemical storage hub in West Africa. Largest private petrochemical hub in West Africa.
28
Pressurised Tanks
5,000 MT
Tank Capacity
35m
Foundation Depth
65%
Completion
"NOTGATE's approach to safety and precision in petrochemical construction is world-class. Their investment in training local welders to international standards has been particularly impressive."