Overview
Construct a 500-bed tertiary hospital to serve as the referral centre for South-East Nigeria. The facility needed surgical theatres, ICU, radiology, maternity, and isolation wards — all built to WHO standards for infection control and patient flow.
Project Facts
- Location
- Independence Layout, Enugu
- Client
- Enugu State Ministry of Health
- Project Type
- Government
- Status
- Completed
- Duration
- 26 Months
- Completion Date
- March 2020
- Services
- Design & Build · Medical Gas Systems · Infection Control · HEPA HVAC · Phased Handover
- Structural Engineer
- NOTGATE Structural Division
- Architect
- Health Facilities Design Group
- Team Size
- 310 workers at peak
The Challenge
Healthcare construction demands precision in MEP systems, infection control, and medical gas infrastructure. The site had limited access for large equipment, and the state required phased handover so emergency services could begin while construction continued.
The Solution
NOTGATE implemented a clean-build protocol with dedicated infection-control officers on site 24/7. Medical gas pipelines, HVAC with HEPA filtration, and uninterruptible power systems were installed by certified specialists. A phased handover saw the emergency department open 8 months before the main hospital, serving the community during the final construction phase.
Project Gallery

Project Impact
The hospital now serves over 2,000 outpatients daily and has performed over 8,000 surgeries in its first three years. It is the first WHO-standard tertiary facility in South-East Nigeria. 2,000+ outpatients daily.
500
Beds
2,000+
Daily Outpatients
8,000+
Surgeries (3yr)
8
Theatres
"NOTGATE built us more than a hospital — they built us a lifeline for the people of Enugu. The quality of construction and the phased delivery approach were exemplary."