Overview
Create a 240-unit waterfront residential estate that would set a new benchmark for luxury living in Lagos. Each unit required smart-home integration, private balconies with lagoon views, and a central clubhouse with marina access.
Project Facts
- Location
- Lekki Phase 2, Lagos
- Client
- Coastal Living Developments
- Project Type
- Residential
- Status
- Completed
- Duration
- 16 Months
- Completion Date
- March 2023
- Services
- Design & Build · Geotechnical Engineering · Smart-Home Integration · Landscape Architecture · Marina Construction
- Structural Engineer
- NOTGATE Structural Division
- Architect
- Studio Lekki
- Team Size
- 190 workers at peak
The Challenge
The site sat on reclaimed land with poor soil bearing capacity. Standard foundations would settle unevenly. Additionally, the client demanded that 40% of units be ready for handover within 10 months to satisfy pre-sales commitments.
The Solution
NOTGATE designed a raft foundation system with geotextile reinforcement and vibro-compaction of the subsoil. A phased construction strategy delivered the first 96 units in 10 months while the remaining 144 units followed 6 weeks later. Smart-home infrastructure was pre-installed during the shell phase to avoid retrofit disruption.
Project Gallery

Project Impact
All 240 units were sold out within 8 weeks of launch. The estate achieved a 98% occupancy rate within 3 months and has become one of the most sought-after addresses on the Lekki peninsula. 100% sold out in 8 weeks.
240
Units
98%
Occupancy
8 Weeks
Sell-Out Time
24
Marina Berths
"NOTGATE turned a challenging site into one of Lagos' most desirable addresses. Their phased delivery strategy saved our pre-sales programme and the quality speaks for itself."